中利#2爐(lu)C修,恒聯環(huan)保(bao)能源有限責任(ren)公(gong)司承(cheng)擔這次(ci)檢修任(ren)務,從9月3日(ri)入廠安(an)全培訓開始到今(jin)天已經進行了10天,恒聯環保中利項目部按照檢修(xiu)項目,逐條落實,各項檢修(xiu)工作正有序開展(zhan)。
這次檢(jian)修的#2爐(lu)是帶有(you)外(wai)置床的鍋爐(lu),相對(dui)沒(mei)有(you)外(wai)置床的鍋爐(lu)檢(jian)修(xiu)任務要爭加三分之一(yi)還(huan)多(duo)。這次不僅有(you)鍋爐(lu)本體(ti)部分檢(jian)修(xiu),還(huan)有(you)外(wai)置床檢(jian)修(xiu);余(yu)熱省(sheng)煤器檢(jian)修(xiu);四(si)臺大型(xing)錐形閥檢(jian)修(xiu);密封筒(tong)更換;刮(gua)板輸煤器、刮(gua)板輸渣器檢(jian)修(xiu);風機檢(jian)修(xiu)等。另外(wai)還(huan)有(you)電除(chu)塵系(xi)統(tong)(tong)、除(chu)灰系(xi)統(tong)(tong)、脫硫系(xi)統(tong)(tong)檢(jian)修(xiu)。
面對(dui)十(shi)分艱巨的檢修(xiu)任務(wu)(wu),恒聯(lian)環保(bao)中利(li)項(xiang)目部召開多次會議,研究檢修(xiu)方(fang)案:首先,按(an)(an)照檢修(xiu)項(xiang)目細分小組,責(ze)任到人(ren);其次每天(tian)按(an)(an)照計劃任務(wu)(wu)安排第(di)(di)二天(tian)要完成的工(gong)作量,該加班(ban)的要加班(ban),確(que)保(bao)每天(tian)檢修(xiu)任務(wu)(wu)完成;第(di)(di)三是加強與業(ye)主(zhu)的溝通,了解檢修(xiu)重(zhong)點(dian),重(zhong)點(dian)要處(chu)理的檢修(xiu)任務(wu)(wu)。恒聯(lian)環保(bao)組織(zhi)近百人(ren)參與檢修(xiu)工(gong)作。通過10天的檢修,到目前為止檢修項目從安全、質量和進度方面可控在控,各項檢修工作正緊張有序開展。